As I mentioned in my last post, we met with our builder Omer Kucuk in my last few days in Biga to draw up a realistic building schedule.

Here is the result:

August 25: Arrival of the roofing supplies
August 26: Installation of the roof
August 27: Installation continued
August 28: Installation of the plumbing system
August 30: Installation of the alum flooring
August 31: Installation continued
September 3: Ceramic flooring
September 4: Ceramic flooring
September 5: Water installation
September 7: Ceiling construction
September 8: Painting interior walls
September 9: Assembling the windows
September 10: Electric work
September 11: Natural gas work
September 12: Natural gas work continued
September 13: Assembling the bathrooms
September 14: Assembling heating system
September 15: Assembling heating system continued
September 16: Outside siding installation
September 17: Outside siding installation continued
September 18: Outside siding installation continued
September 19: Platform stairs
September 20: Assembling the garden tiles
September 21-23: Organizing the garden
September 24: Arranging the kitchen appliances/furniture
September 25: Finishing any incomplete work
September 26: Furnishing the building

As you can see, with this schedule the center should be finished within a month!

I'll be updating you as the plan plays out...:)

all my best,
Jill